Iran Projects

PROJECT NAME: Esfahan metro Tunnels
EMPLOYER: Esfahan Urban Railway Organization (EURO)
CONTRACTOR: Alamoot Co
TBM TYPE: S-227&S-228 EPB Shield (Herrenknecht)
PROJECT STATUS: Ongoing

PROJECT NAME: Kouhrang Water Conveyance Tunnel
EMPLOYER: Esfahan Regional Water Board
CONTRACTOR: Tablie Co
TBM TYPE: S-123 Hard Rock Open Shield (Herrenknech
ROJECT STATUS: Ongoing

PROJECT NAME: Gavoshan Water Conveyance Tunne
EMPLOYER: West Regional Water Organization
CONTRACTOR: Jahad Tose Manabe Ab (JTMA)
TBM TYPE: S-112 Hard Rock Open Shield (Herrenknecht)
PROJECT STATUS: Finished

PROJECT NAME: Tehran-Karaj Water Conveyance Tunnel
EMPLOYER: Ab-Niroo
CONTRACTOR: Hara Institute
TBM TYPE: S-323 Hard Rock Double Shield (Herrenknecht)
PROJECT STATUS: First lot Finish, Second lot Ongoing

PROJECT NAME: West Region Water Conveyance Tunnel lot 1
EMPLOYER: Ab-Niroo
CONTRACTOR: G.H Co
TBM TYPE: S-357 Hard Rock Double Shield (Herrenknecht)
PROJECT STATUS: Ongoing

PROJECT NAME: West Region Water Conveyance Tunnel lot 3
EMPLOYER: Ab-Niroo
CONTRACTOR: G.R Co
TBM TYPE: S-157 Hard Rock Double Shield (Herrenknecht & Seli)
PROJECT STATUS: Ongoing 
PROJECT NAME: Dez Ghomroud Water Conveyance Tunnel lots1&2
EMPLOYER: Ab-Niroo
CONTRACTOR: Sabir Co
TBM TYPE: S-338 EPB, Hard Rock Single Shield (Herrenknecht)
PROJECT STATUS: Ongoing

PROJECT NAME: Shiraz metro Tunnels
EMPLOYER: Shiraz Urban Railway Organization (SURO)
CONTRACTOR: Bamrah
TBM TYPE: EPB Shield (NFM)
PROJECT STATUS: Ongoing 
PROJECT NAME: Tabriz metro Tunnels
EMPLOYER: Ghatar shahri (Subway)
CONTRACTOR: Alamot Co
TBM TYPE: EPB machine(wirth)
PROJECT STATUS: Ongoing

PROJECT NAME: Dez Ghomroud Water Conveyance Tunnel lots 5
EMPLOYER: Ab Niroo
CONTRACTOR: Fater Institute
TBM TYPE: Hard Rock Double Shield (Wirth)
PROJECT STATUS: Finish

PROJECT NAME: Dez Ghomroud Water Conveyance Tunnel lots 3&4
EMPLOYER: Ab Niroo
CONTRACTOR: Fater Institute
TBM TYPE: Hard Rock Double Shield (Wirth)
PROJECT STATUS: Finish

PROJECT NAME: Tehran_Shomal High way (Alborz) Tunnel
EMPLOYER: Tehran High Way Organization
CONTRACTOR: Taloon Co
TBM TYPE: Hard Rock Open Shield (Wirth)
PROJECT STATUS: Finished

PROJECT NAME: Tehran Sewage project, Khayam-Bahmanyar
EMPLOYER: Khakriz Ab
CONTRACTOR: Aksa & Alamoot Co
TBM TYPE: ME 170, EPB Shield (Lovat)
PROJECT STATUS: Finished

PROJECT NAME: Tehran metro line 3
EMPLOYER: Tehran Urban Railway Organization (TURO)
CONTRACTOR: Sabir International Co
TBM TYPE: S-523 EPB Shield (Herrenknecht)
PROJECT STATUS: TBM assembly

PROJECT NAME: Mashad metro
EMPLOYER: Mashad Urban Railway Organization (MURO)
CONTRACTOR: Rahab institute
TBM TYPE: EPB Shield (NHI Technology)
PROJECT STATUS: TBM assembly

PROJECT NAME: Ahvaz metro
EMPLOYER: Ahzaz Uban Railway Organization (AURO)
CONTRACTOR: Keyson.Co
TBM TYPE: EPB Shield (NHI Technology)
PROJECT STATUS: TBM assembly